Chinese New Year 2027 Shipping Deadlines: Complete Cut-Off Calendar & Planning Guide
· By SinoShipment
Chinese New Year 2027 falls on Saturday, February 6 — eleven days earlier than the 2026 holiday on February 17. If you are planning with last year’s calendar, your “order by” date will arrive after the factories have already gone dark.
That is not a rounding error. It is the difference between your cargo sailing on the last available vessel and sitting in a closed factory until March. Every importer who has been through a CNY cycle knows the pattern: rates spike, containers vanish, vessels blank, and the scramble of mid-January rewards only those who booked in December. The difference in 2027 is that the window to act is narrower by nearly two weeks.
This guide gives you the complete chain of cut-offs — from production order deadlines in late November 2026 to last air freight bookings in late January 2027 — with lane-by-lane ocean sailings, an Amazon FBA buffer playbook, historical rate impact data, the post-holiday recovery timeline, and a printable checklist. We run the China booking desk at Sinoshipment, a Shenzhen-based freight forwarder that has moved cargo from China to the world since 2013 for more than 5,000 clients, and every date below comes from what we see at the port, not what a desk overseas assumes.

Key Takeaways
- CNY 2027 = Saturday, February 6 (Year of the Goat). The statutory holiday is expected February 5–8, but the economic shutdown runs roughly 6–8 weeks: mid-January through mid-March 2027.
- Eleven days earlier than 2026 — the planning runway is compressed. Production orders must be finalised by November 28–December 12, 2026 (8–10 weeks before the holiday, per SEKO Logistics).
- Last FCL ocean sailings fall in mid-to-late January 2027: US West Coast ~Jan 18–23; US East Coast ~Jan 10–15; Europe ~Jan 12–18; Middle East ~Jan 20–25; Australia ~Jan 22–27. All are planning estimates, not carrier guarantees.
- Rate impact (based on 2026 CNY data): blank sailings up 38%, peak season surcharges of $1,500–$2,500 per FEU, air freight rates spike 20–30%, port loading rates drop up to 40%.
- Amazon FBA buffer: plan 8–12 weeks of cover on China-sourced SKUs. Keep 30–60 days at FBA; stage the rest at a 3PL.
- Recovery window (Feb 20–Mar 15): workforce at ~35% post-holiday, first reliable post-CNY sailings around March 3, full capacity by mid-March.
1. When Is Chinese New Year 2027 and Why Does It Come Earlier?
Chinese New Year 2027 falls on Saturday, February 6, 2027, marking the start of the Year of the Goat. The lunar calendar follows a roughly 354-day year against the 365-day solar year, which means the holiday shifts about eleven days earlier each year unless a leap month intervenes. The progression is predictable: 2024 was February 10 (Dragon), 2025 was January 29 (Snake), 2026 was February 17 (Horse), and 2027 lands on February 6 — pulling the entire pre-holiday shipping season forward by eleven days compared to what most importers experienced last year.
The State Council has not yet published the official 2027 holiday schedule as of October 2026 — it normally arrives in late autumn — but the statutory break is expected to cover New Year’s Eve plus the first three days of the lunar year, approximately February 5–8. Some sources circulate February 17 as the 2027 date; that is the 2026 date, and following it will put your planning eleven days behind reality.
The practical consequence is simple and severe: if you used last year’s timeline as your template, every cut-off in your plan — production order, ocean booking, last sailing — is eleven days too late. The runway between “start planning” and “factories closed” is shorter, and the competition for pre-holiday vessel space is more concentrated.
2. What Is the CNY 2027 Factory Shutdown Timeline?
The legal holiday is about four to seven days. The economic shutdown is six to eight weeks. That gap is where most importers get burned — they plan for the statutory dates and forget that factories begin winding down weeks earlier and take weeks to restart.
Based on how Chinese manufacturers and logistics operators handled the 2026 closure, and on SEKO Logistics’ planning guide for 2027, here is the real timeline:
| Phase | Approximate Window | Workforce Level | What Happens |
|---|---|---|---|
| Pre-holiday wind-down | Jan 9–16, 2027 | 80–90% | Migrant workers begin leaving; new orders harder to place; freight rates start climbing |
| Progressive shutdown | Jan 16–30, 2027 | 50–80% | Many factories stop accepting new orders; rush-order cut-off hits; container space tightens sharply |
| Complete shutdown | Jan 30–Feb 14, 2027 | 0–10% | Full stop. Ports at 20–30% capacity; customs, banks, and forwarders largely closed |
| Partial restart | Feb 20–Mar 6, 2027 | 35–60% | Pre-holiday backlog processed first; new production slow; quality variable with new/temp workers |
| Stabilisation | Mar 6–20, 2027 | 80–100% | Nameplate capacity reached; quality settling through late March |
The hardest-hit regions are Guangdong (Shenzhen, Dongguan, Guangzhou) and Zhejiang (Yiwu, Ningbo), where workforces are predominantly migrant. Workers in these provinces head home during the chunyun migration — the world’s largest annual human migration — which begins around February 7, 2027. Absenteeism can exceed 30% even before the statutory holiday begins.
Our Industry Insight — From the Shenzhen Booking Desk
In our experience managing pre-CNY shipments from Shenzhen and Yantian, Guangdong factories rarely announce their exact closing date before late December. When they do, it is often a phone call, not a formal notice. We require every client to get their supplier’s last-production-day and reopening date in writing — ideally with the production manager’s name attached. A factory that says “we close around February 1” has effectively closed for you on February 1, regardless of what the carrier schedule says. In 2026, one of our electronics clients lost a full container’s worth of production because their Dongguan supplier stopped accepting orders on January 18 — nine days before they said they would.
3. What Are the Last Ocean Freight Sailings Before CNY 2027?
For FCL shipments, the last realistic vessel departures before the CNY shutdown fall in mid-to-late January 2027. The exact date depends on your origin port, destination, and transit time — but the principle is the same for every lane: you need finished, packed, and customs-cleared cargo ready to load before the carrier’s cut-off, which moves earlier as the holiday approaches.
SEKO Logistics advises booking ocean space 3–4 weeks before your planned departure date (4–5 weeks at the peak), meaning bookings should be confirmed by mid-to-late December for January sailings. LCL consolidation closes 5–7 days earlier than FCL because the consolidation and deconsolidation process adds time.
Here is the lane-by-lane guide to last sailings. All dates are planning estimates based on transit-time calculations and historical CNY patterns — not carrier guarantees. Confirm with your forwarder for specific vessel schedules.
| Origin → Destination | Mode | Last ETD (Estimate) | Typical Transit | Book Ocean By |
|---|---|---|---|---|
| Shanghai/Yantian → Los Angeles/Long Beach | FCL 40HC | Jan 18–23, 2027 | 14–20 days | Late Dec 2026 |
| Shenzhen → New York/New Jersey | FCL 40HC (all-water) | Jan 10–15, 2027 | 25–35 days | Mid-Dec 2026 |
| Ningbo → Felixstowe/Rotterdam | FCL 40HC | Jan 12–18, 2027 | 25–35 days | Mid-Dec 2026 |
| Shenzhen → Jebel Ali (Dubai) | FCL 40HC | Jan 20–25, 2027 | 15–25 days | Late Dec 2026 |
| Shenzhen → Sydney/Melbourne | FCL 40HC | Jan 22–27, 2027 | 12–18 days | Late Dec 2026 |
| Shanghai → Santos (Brazil) | FCL 40HC | Jan 8–13, 2027 | 35–45 days | Early Dec 2026 |
| Yiwu/Guangzhou → Global | LCL consolidation | Jan 10–18, 2027 | +5–7 days vs FCL | Early Dec 2026 |
Transit times follow the standard benchmarks: 14–20 days to the US West Coast, 25–35 days to the US East Coast, 25–35 days to Europe (15–20 days via China-Europe rail), 15–25 days to the Middle East, and 12–18 days to Australia. For a deeper comparison of FCL versus LCL for your shipment size, see our guide to FCL vs LCL shipping from China to the USA.
The calculation behind each date is straightforward: count backward from February 6 (or from when you need the goods to arrive) by the transit time plus a buffer for pre-holiday congestion. A container that takes 18 days from Yantian to Long Beach must sail by approximately January 20 to arrive before the port slowdown — and in practice, you want it to arrive before the shutdown, not during it.
A critical risk that does not appear in any carrier schedule: container and equipment shortages. As every importer in China rushes to ship at the same time, empty container inventories at origin ports become extremely tight. Booking a vessel slot does not guarantee that a 40HC will be available to stuff. We advise clients to secure equipment at least two weeks before the booking date, and to consider alternative origin ports — Xiamen or Lianyungang can have better equipment availability than Shenzhen or Shanghai during the peak rush.
For the full scope of our ocean freight services — FCL, LCL, and door-to-door from every major Chinese port — see our sea freight from China service page.
4. When Should You Book Air Freight Before CNY 2027?
Air freight gives you a later window than ocean — but it is not a rescue plan you can activate at the last minute. SEKO Logistics recommends booking air 1–2 weeks before the holiday, with last flights around February 3–5, 2027. That gives you roughly 10–15 extra days of production runway compared to ocean, but capacity is fully booked from the first week of February, and rates climb steeply into the peak.
Here is how the air freight window compares to ocean:
| Factor | Ocean Freight | Air Freight |
|---|---|---|
| Last departure | Mid-to-late January | ~Feb 3–5, 2027 |
| Typical transit | 14–35 days | 3–7 days |
| Rate trend into CNY | PSS $1,500–2,500/FEU | +20–30% per kg |
| Book by | Mid-to-late December | Late January |
| Best for | Bulk, replenishment | Urgent restocks, high-value/low-weight |

Based on 2026 CNY data, air freight rates typically rise 20–30% during the pre-holiday peak, and the cheapest options sell out first. If you are moving 100–500 kg of electronics or samples, the rate difference between a December booking and a late-January booking can be $1.50–$3.00 per kilogram — which on a 300 kg shipment is $450–$900, enough to erase the margin on lower-priced goods.
The practical strategy is a hybrid split: book the bulk of your inventory by ocean in December, and hold a small air freight budget in reserve for January gaps. If the ocean shipment arrives on time, you save the air cost. If it is delayed or rolled — which happens to roughly 15–20% of pre-CNY bookings — the air reserve keeps your shelves stocked while you wait.
When air freight pays: recovery cargo (an ocean container stuck behind a blanked sailing), launch stock for a new product, and high-value goods where the per-unit freight cost is a small fraction of the selling price. When it does not: bulk inventory with margins below ~40%, where the air cost per unit exceeds the profit per unit.
For our full air freight capabilities — direct and consolidation services from Shenzhen, Shanghai, and Hong Kong — see our air freight from China page.
5. How to Plan Your Shipping Calendar: October 2026 to March 2027
The biggest mistake importers make is treating Chinese New Year as a February problem. By February, the problem is already solved or already lost. The planning starts in October.
Here is the month-by-month calendar, with specific actions and the reasoning behind each deadline:
| Month | Key Actions | Why It Matters |
|---|---|---|
| October 2026 | Audit every China-sourced SKU for CNY exposure. Ask each supplier, in writing, for their actual last production date and reopening date. Place buffer POs on your top-selling SKUs. | Production slots are still open at normal pricing. Carrier Q1 2027 schedules are being released — ask your forwarder for confirmed sailing programmes. |
| November 2026 | Finalise production orders by Nov 28–Dec 12 (8–10 weeks before CNY). Book ocean space for December departures. Last comfortable LCL PO window closes mid-month. | This is the decision month for sea freight. December is already the exception case; by January, you are negotiating for space on someone else’s cancelled booking. |
| December 2026 | Ship the bulk by ocean. Early-December sailings are the last low-stress departures. Route buffer containers to a 3PL or prep centre, not straight to FBA. | Rates begin climbing mid-December. Container and equipment availability tightens. Documentation must be prepared and signed before offices close. |
| January 2027 | Book air freight for gaps (first half of month). Monitor port congestion and vessel schedules. Confirm post-CNY production slots for March restart. Last ocean sailings mid-to-late January. | Rush-order cut-off hits early-to-mid January. Air window closes late January. This is the final scramble — expect premium pricing and rolled bookings. |
| February 2027 | Factories are dark. You are selling from buffer inventory. No new production is possible. Monitor port conditions for post-holiday backlog. | Complete shutdown Jan 30–Feb 14. Even after factories “reopen,” capacity is at ~35% for the first week. |
| March 2027 | Confirm production restart. Book first post-CNY sailings (~Mar 3). Expect quality settling through late March. Plan Q1 restocking. | Workforce ramps from 35% to 80–100% by mid-March. Post-CNY space is as tight as pre-CNY — book early. |
The method that makes this calendar work is reverse calculation: start from the date you need goods in your warehouse, subtract transit time, subtract production lead time, subtract a 2–3 week CNY buffer, and the result is your order placement deadline.
Worked example: You need goods in a US warehouse by February 1, 2027. US West Coast transit is 14–20 days. Production lead time for your product is 30 days. CNY buffer is 14 days (for pre-holiday congestion). Working backward: February 1 − 20 days transit − 30 days production − 14 days buffer = November 3–10, 2026 — your order placement deadline. If you wait until December to place this order, it will not arrive before the shutdown.
Our Industry Insight — The 70/30 Split
For most of our clients at Sinoshipment, the strategy that works is a 70/30 split: book 70% of your pre-CNY volume by ocean in December at the best available rate, and hold 30% as an air freight reserve for January gaps. This is not the cheapest plan — it is the plan that survives the most failure modes. In January 2026, we had three clients whose ocean bookings were rolled to post-holiday sailings because of blank programmes. The two who had air reserves kept selling through February. The one who did not lost three weeks of sales. As a forwarder based in Shenzhen since 2013, we have been through every CNY cycle — and the lesson is always the same: plan for the vessel to be late, and the air bridge is your insurance.
6. Amazon FBA and E-Commerce Sellers: Your CNY 2027 Playbook
For Amazon FBA sellers and e-commerce operators sourcing from China, CNY is not just a shipping problem — it is an inventory survival problem. A stockout during February and March can tank your Best Seller Rank, trigger the low-inventory-level fee, and hand your Buy Box to a competitor. Here is how to plan for it.
The buffer rule: Plan 8–12 weeks of inventory cover on every China-sourced SKU. Calculate it as: weekly sales velocity × gap weeks (8–12) − units already in transit. If you sell 100 units per week and expect a 10-week gap, you need 1,000 units of buffer minus whatever is already on the water.
The two-stage structure: Do not send all 8–12 weeks of buffer to Amazon at once. Amazon’s storage fees and aged-inventory charges will eat your margin, and the low-inventory-level fee floor (28 days of supply) does not require you to overstock. Instead:
- Keep 30–60 days of supply at Amazon FBA — enough to stay above the low-inventory-fee floor with a margin for a February demand bump.
- Stage the remainder at a domestic 3PL or prep centre — received in December and January, palletised, and held outside Amazon’s fee clock.
- Feed FBA in waves every 2–3 weeks through February and March, sized against actual sales velocity rather than an October forecast.
De minimis is gone. Since the elimination of the de minimis exemption (China/HK in May 2025, all countries in August 2025), every parcel entering the US requires formal entry. For FBA sellers without US import status, a DDP arrangement under your forwarder’s bond is the default model — the forwarder handles customs clearance, duty payment, and delivery to the Amazon fulfilment centre. For a full breakdown of the tariff landscape that affects your landed cost, see our guide to US import tariffs in 2026.
Last-sail timeline for FBA sellers: Ocean freight to the US West Coast (14–20 days) + deconsolidation at destination (3–5 days) + FBA inbound processing (7–14 days) = total lead time of 24–39 days from vessel departure to units available for sale. If you need FBA stock by February 1, your ocean shipment must sail by approximately December 24–January 9 — well before the last-sailing cut-offs in Section 3.
For our full Amazon FBA service — consolidation at Shenzhen, labelling and palletising, duty-paid delivery to global Amazon fulfilment centres — see our Amazon FBA forwarding page.
7. How Much Do Freight Rates Rise During Chinese New Year?
Every CNY cycle follows the same rate pattern: a pre-holiday surge as demand spikes and capacity withdraws, a brief lull during the shutdown, and a post-holiday elevation as backlogs clear and capacity returns slowly. The 2026 cycle provides the most recent and most relevant data for planning 2027.
| Metric | 2026 CNY Data | Source | 2027 Planning Implication |
|---|---|---|---|
| Blank sailings (February) | 107 sailings (+38% vs projections) | Zendrop / cogoport | Expect similar blank programmes; Q1 2027 schedules released Oct–Nov 2026 |
| Peak season surcharge | $1,500–$2,500 per FEU | Zendrop | Budget for PSS on top of base rate; confirm all-in quotes |
| Air freight rate increase | 20–30% | Zendrop | Book air early; cheapest tiers sell out first |
| Port loading rate drop | Up to 40% | sendfromchina | Expect longer dwell times and customs delays |
| Drayage cost increase | 200–300% vs normal | ASL India | Budget for elevated inland transport at both ends |
| Post-CNY transit extension | 35 → ~40 days (China→USWC) | Flexport OTI | Add 5–7 days to post-holiday transit estimates |
| Pre-CNY import volume surge | 20–30% above normal (USWC) | Zendrop | Space competition is fierce; book early or pay premium |

Why rates spike: Three forces collide simultaneously. First, demand surges as every importer tries to move goods before the shutdown — US West Coast import volumes jump 20–30% above normal. Second, carriers withdraw capacity through blank sailings to prevent overcapacity during the low-demand shutdown period — in 2026, this meant 107 blanked sailings in February alone. Third, equipment and labour shortages at ports compound the effect: container loading rates drop by up to 40%, and drayage costs can rise 200–300%.
2027 specifics: Blank sailing programmes for Q1 2027 will be announced as carriers finalise their schedules, typically starting in October or November 2026. Far East–Northern Europe loops historically see the heaviest CNY-related capacity cuts, with reduced weekly departures particularly affecting sailings from Shanghai and Ningbo. Ask your forwarder for the confirmed blank-sailing programme as soon as it is released.
Mitigation strategies:
- Contract vs. spot: A volume contract with your freight forwarder locks in both space and rate. Spot shippers compete for every booking with everyone else — and in January, that competition is brutal.
- Book early: The single most effective rate mitigation is booking in December rather than January. December bookings lock in pre-surge pricing; January bookings pay the premium.
- Diversify carriers and routes: Spreading cargo across multiple carriers and alternative routings reduces the risk of a single blanked sailing derailing your plan.
- Compare all-in quotes, not base rates: Published FAK base rates can look attractive; the surcharge stack (PSS, BAF, EIS, congestion, origin/destination charges) can equal the base rate. Always compare all-in.
For the complete guide to current China-to-US freight costs and rate trends — including the Q4 2026 post-Golden Week market that sets the stage for the pre-CNY surge — see our analysis of China to US shipping costs in Q4 2026. For a deeper look at FCL container shipping from China, including rate structures and transit benchmarks, see our FCL shipping from China to the USA guide.
8. What Happens After CNY: The Recovery Window (Feb 20–March 15)
Most CNY guides end at “book before the holiday.” But the post-holiday recovery window — roughly February 20 to March 15 — is when a different set of risks emerges, and importers who plan only for the pre-CNY rush get caught again.
The restart is not a switch. Factories reopen around mid-February but at only about 35% of normal workforce. Migrant workers return gradually over 2–3 weeks, and full capacity is typically not reached until mid-March. In the first week back, production lines prioritise pre-holiday backlog — orders that were placed and paid for before the shutdown — meaning new orders placed in February may not start production until March.
The first reliable post-CNY sailings depart around March 3, 2027. Earlier departures exist but carry elevated risk: port congestion from pre-holiday backlog, equipment repositioning delays, and reduced vessel frequency from blank programmes that have not yet fully unwound.
Quality risk: The first 2–3 weeks after reopening are historically the most error-prone period in Chinese manufacturing. New and temporary workers, combined with rushed production to clear backlog, can lead to quality issues that do not surface until the goods reach your warehouse. If you have a pre-shipment inspection (PSI) arrangement, insist on it for every post-CNY shipment — especially in March.
Booking strategy for March: Post-CNY vessel space is often as tight as pre-CNY space, because the backlog of delayed and rolled cargo competes with new shipments for limited capacity. Book March sailings in January — before the shutdown — to secure priority space for the restart.
Rate expectation: Rates stay elevated for 2–3 weeks after the holiday as backlogs clear and capacity returns slowly. Based on 2026 data, post-CNY transit times from China to the US West Coast extended from 35 to approximately 40 days. Plan for 5–7 extra days of transit on post-holiday shipments.
For customs clearance support during the recovery window — when port congestion and documentation backlogs can delay release — see our customs clearance services.
9. Your Chinese New Year 2027 Shipping Checklist
Here is a consolidated checklist organised by category, with specific action items and their deadline windows:
Supplier Communication (October–November)
- Confirm each supplier’s last production day and reopening date in writing
- Ask for the production manager’s name and direct contact
- Identify backup suppliers for critical SKUs
- Confirm whether your supplier will process post-CNY backlog before accepting new orders
Production Planning (October–December)
- Place POs by November 28–December 12 (8–10 weeks before CNY)
- Pay 30% deposit to lock production slots
- Prioritise A-SKUs (top sellers) before routine replenishment SKUs
- For bespoke/tooled products: order by early October 2026 (additional 4–6 weeks lead time)
Ocean Booking (November–January)
- Book ocean space by mid-to-late December (3–4 weeks before January departures; 4–5 weeks at peak)
- Secure container equipment 2 weeks before booking date
- Confirm vessel name, voyage number, and blank-sailing status
- Ask your forwarder: all-in itemised quote, rollover policy, free time and detention terms
- Track the confirmed Q1 2027 blank-sailing programme (released Oct–Nov 2026)
Air Reserve (January)
- Hold an air freight budget for gap coverage (typically 20–30% of volume)
- Book air by late January (1–2 weeks before holiday)
- Identify priority SKUs for air bridge (high-value, low-weight, stockout-critical)
- Confirm chargeable weight calculation (volumetric ÷ 6,000)
Inventory Buffer (November–January)
- Calculate 8–12 weeks of cover on China-sourced SKUs
- Keep 30–60 days at FBA; stage remainder at domestic 3PL
- Plan wave-feeding cadence (every 2–3 weeks through February–March)
- Route December buffer containers to prep centre, not straight to FBA
Documentation (December–January)
- Commercial Invoice — signed and accurate
- Packing List — matching PI quantities and weights
- Bill of Lading / Airway Bill — draft confirmed before offices close
- Certificate of Origin (CO / Form A / Form E) — if required for preferential duty
- MSDS and transport鉴定报告 — for battery-powered, liquid, or powder goods
- Fumigation Certificate — for wood-packaged cargo
Post-CNY Recovery (January + March)
- Confirm March production slots in January (before shutdown)
- Book first post-CNY sailings (~March 3) in advance
- Schedule pre-shipment inspections for all March shipments
- Plan for 5–7 extra days of transit on post-holiday shipments
- Expect quality settling through late March; hold a QC buffer
10. FAQ
When is Chinese New Year 2027? Chinese New Year 2027 falls on Saturday, February 6, 2027 — the Year of the Goat. The statutory holiday is expected to run February 5–8 (Eve plus three days), though the official State Council schedule has not yet been published as of October 2026.
How long do Chinese factories close for Chinese New Year 2027? The legal holiday is approximately 4–7 days, but the real economic shutdown spans 6–8 weeks: factories begin reducing capacity around January 9–16, reach complete shutdown around January 30–February 14, restart at roughly 35% workforce from February 20, and return to normal capacity by March 6–20.
What is the last sailing date before CNY 2027? For FCL ocean freight, the last realistic departures fall in mid-to-late January 2027, varying by lane: US West Coast ~January 18–23, US East Coast ~January 10–15, Europe ~January 12–18, Middle East ~January 20–25, and Australia ~January 22–27. LCL consolidation closes 5–7 days earlier. These are planning estimates — confirm with your forwarder.
When should I book ocean freight before Chinese New Year 2027? Book ocean space 3–4 weeks before your planned departure (4–5 weeks at peak), meaning bookings should be confirmed by mid-to-late December 2026. For long transit lanes (US East Coast, Europe, South America), book by early December. For shorter transit lanes (Middle East, Australia), late December may suffice.
How much do freight rates increase during Chinese New Year? Based on 2026 CNY data, expect peak season surcharges of $1,500–$2,500 per FEU on ocean freight, blank sailings increasing by approximately 38%, air freight rates rising 20–30%, port loading rates dropping up to 40%, and drayage costs increasing 200–300%. Rates stay elevated for 2–3 weeks after the holiday.
How much inventory should I stock before CNY 2027? Plan 8–12 weeks of cover on China-sourced SKUs, calculated as weekly sales velocity multiplied by gap weeks, minus units already in transit. For Amazon FBA sellers, keep 30–60 days at FBA and stage the remainder at a domestic 3PL, feeding FBA in waves every 2–3 weeks.
Can I still ship by air during Chinese New Year? Air freight operates closer to the holiday than ocean — last flights are around February 3–5, 2027 — but capacity is fully booked from the first week of February and rates spike 20–30%. Air is best used as a bridge for urgent restocks and high-value cargo, not for bulk inventory. Book 1–2 weeks before the holiday.
When do factories reopen after CNY 2027? Factories begin reopening around February 20, 2027, but at only about 35% of normal workforce. Capacity reaches 40–60% by late February, 80–100% by mid-March, with quality settling through late March. The first reliable post-CNY ocean sailings depart around March 3.
What happens if my shipment gets rolled during CNY? A rolled booking means your container is bumped to a later vessel — typically adding 1–2 weeks of delay. During the pre-CNY peak, rollover rates increase because vessels are overbooked. Mitigation: book early, confirm the vessel and voyage number, ask your forwarder about rollover policy, and hold an air freight reserve for critical cargo. For more on transit time expectations, see our guide on how long shipping takes from China to the USA.
How does CNY 2027 affect Amazon FBA sellers? CNY creates a 6–8 week gap in production and shipping. Without buffer inventory, FBA sellers face stockouts that trigger low-inventory fees, lost Buy Box, and damaged Best Seller Rank. Plan 8–12 weeks of cover, keep 30–60 days at FBA, stage the rest at a 3PL, and feed FBA in waves. Since de minimis is eliminated, use DDP under your forwarder’s bond for duty-paid delivery. See our Amazon FBA forwarding service for consolidation, labelling, and global delivery.
Conclusion: Plan the Window, Don’t Chase the Deadline
Chinese New Year 2027 is February 6 — eleven days earlier than 2026, and the economic shutdown runs six to eight weeks, from mid-January through mid-March. The chain of cut-offs starts with production orders in late November and ends with the last air flights in early February. Rate impact is predictable: peak surcharges, blank sailings, equipment shortages, and air spikes. Recovery takes until mid-March, and the first weeks back are the most error-prone of the year.
The importers who navigate CNY successfully are not the ones who find a clever last-minute workaround. They are the ones who started in October, placed orders in November, booked ocean in December, held an air reserve for January, and staged buffer inventory at a 3PL so they could keep selling while China was closed.
At Sinoshipment, we sit at the booking desk in Shenzhen and Yantian — not in an office overseas reading carrier advisories. We have moved cargo from China to the world since 2013 for more than 5,000 clients, through every CNY cycle, and we secure vessel space before overseas agents see the allocation. We provide itemised all-in quotes with no hidden fees, manage DDP and FBA lanes end-to-end, and give you a straight answer on which shipments should sail and which should fly.